Royal Mail / Solystic
Independent sign-off at four hubs
- Fault
- Multi-million-pound parcel sorting machines at Southampton, Wolverhampton, Northern Ireland and Birmingham had to be commissioned, validated and handed over to contractual service levels.
- Diagnosis
- Acceptance could not rest on the OEM's own account of readiness.
- Action
- Independent technical governance over commissioning, validation and handover (April 2021 to August 2022). Controlled the technical sign-off that released milestone capital payments to the OEM, holding acceptance until punch-list items were closed. Upskilled local maintenance teams, decentralised critical spares and turned OEM schematics into site procedures. In 2025, as Lead Project Engineer, led the design and commissioning of a new-build AGV sortation system at the Northampton SuperHub and built its PPM scheme from nothing.
- Result
- Live-trial throughput verified above 7,000 parcels per hour against contractual service levels before handover.
Start a conversation
Bring the failure that won't stay fixed.
Interim, contract and project engagements across the UK.